Portfolio CPI is 0.85 — below 1.00
highImpact -USD 6.0MWeighted CPI across 1 project(s) is under target. 0 project(s) in critical zone, 1 at risk. Estimated cost overrun USD 6.0M.
Illustration with sample data. Start free with your own project →
Full root cause analysis, group performance breakdown, and recovery recommendations — updated each time you add a reporting period. Findings derive from your real portfolio EVM and BOQ data, never synthetic numbers.
Weighted CPI across 1 project(s) is under target. 0 project(s) in critical zone, 1 at risk. Estimated cost overrun USD 6.0M.
Schedule Variance is -USD 3.8M. At current pace, completion projects 111% of baseline duration unless corrective action is taken.
16 BOQ item(s) in Concrete are running over plan. Earned USD 8.2M vs actual USD 9.5M. Drill into Cost Drivers to see the items.
10 item(s) trending negative with cost variance -USD 354.0K. Review unit rates and scope creep before it grows.
At the current CPI, EAC exceeds BAC by USD 8.6M. Recovery scenarios needed.