AI Insights

Rule-based

Full root cause analysis, group performance breakdown, and recovery recommendations — updated each time you add a reporting period. Findings derive from your real portfolio EVM and BOQ data, never synthetic numbers.

Findings
5
Critical
0
Cost Variance
-USD 6.0M

Portfolio CPI is 0.85 — below 1.00

highImpact -USD 6.0M

Weighted CPI across 1 project(s) is under target. 0 project(s) in critical zone, 1 at risk. Estimated cost overrun USD 6.0M.

Portfolio SPI is 0.90 — schedule slipping

high

Schedule Variance is -USD 3.8M. At current pace, completion projects 111% of baseline duration unless corrective action is taken.

Concrete is the largest cost driver (71% of overrun)

highImpact -USD 1.3M

16 BOQ item(s) in Concrete are running over plan. Earned USD 8.2M vs actual USD 9.5M. Drill into Cost Drivers to see the items.

Rebar is the next driver to watch

mediumImpact -USD 354.0K

10 item(s) trending negative with cost variance -USD 354.0K. Review unit rates and scope creep before it grows.

Forecast at completion is USD 57.1M

highImpact -USD 8.6M

At the current CPI, EAC exceeds BAC by USD 8.6M. Recovery scenarios needed.